Workshop Extension and Updates

This site may earn a commission from merchant affiliate
links, including eBay, Amazon, Skimlinks, and others.

Again, to keep things nice and tight, I ended up with one of the anchor bolts on each side inside the column. So I epoxied the anchor bolts and base plate in place and then welded the columns to the baseplates.

57.webp
58.webp
59.webp
60.webp
 
Getting the beam into place got a bit interesting - particularly doing it all by myself. The ratchet straps got it 80% of the way up and then the HF lift table and a few blocks were able to push it the last part of the way. Again, once everything was in place it was all welded.

62.webp
65.webp
66.webp
 
is there a reason that you went with bolts instead of all-thread?

I could have epoxied all-thread in place, put the base plate over them, and then used nuts to tie it down, but it was just as easy to epoxy the bolts in place.
 
Next step was the ridge beam. I wanted a cathedral ceiling in this space for the headroom and also wanted to be able to use the beam as a lifting point. Spanning over 20’ meant that was one big-a** beam! I had initially been convinced to go with an LVL, but when it was delivered it was half again as heavy as they had told me to expect. For doing things yourself, that makes a difference. I really should have just stuck with steel. And I think I need some IH8MUD stickers for the mini-excavator...

67.webp
68.webp
69.webp
 
I cut through the roof of the existing workshop and down through the wall framing so that I could run the column down to the knee wall. Then it was just a matter of threading the column down through the hole from the top. One advantage of using steel over wood is that you can “fix” it. I had some existing wiring runs that would have been a pain to pull out or re-run. So I notched the column.

70.webp
71.webp
72.webp
73.webp
74.webp
 
Here’s the slice being welded back into the column and shots of the beam saddles lined up and ready for the beam. I used a roof vent boot and some peel-n-stick flashing to seal up the column through the roof temporarily.

80.webp

76.webp
77.webp
 
Then it was a matter of lifting that big honkin’ beam into place. Let’s just say it wasn’t pretty but nobody got injured and leave it at that… ;)

81.webp
82.webp
83.webp
 
From there it was just a matter of cutting and placing the rafters and then sheathing the roof.

86.webp
88.webp
89.webp
90.webp
 
The local surplus store had a five-gallon bucket of grey paint for $20, so I put that down on the sheathing to give me some more time to work. Again, working by myself meant that I wasn’t out there every day for eight hours until it got done. So the paint helped keep things from deteriorating.

92.webp
93.webp
94.webp
95.webp
 
Tar paper and shingles went down pretty quickly. Fast enough that I didn’t really get “in progress shots” of that stage.

97.webp
98.webp
99.webp
 
Finished up framing the end wall under the roof and then got the walls wrapped with Tyvek.

100.webp
101.webp
 
The next step was getting things closed in by installing the overhead door. It’s not complicated, but there was a bit of trial and error to get everything adjusted right. I’m sure an installer would know all the tricks and get it on the first try. The basic steps were assembling all the hardware onto the door panels, putting the vertical tracks up on either side of the opening, and then just stacking the panels in the tracks and connecting them. The spring and “horizontal” tracks (these were diagonal, since they follow the roof pitch) were then installed and the spring was wound to apply tension.

102.webp
103.webp
104.webp
107.webp
108.webp
 
Then siding and trim - and that is where it currently stands. I’m working on finishing up the soffits and then have to paint to get the outside finished up. From there I have to pour the concrete floor and get it all wired up inside.

109.webp


110.webp


112.webp
 
You should bond that steel to your electrical service, ground rod, or something, with the way that romex is run through the steel. When it shorts out on that steel you will want that breaker to open, not energize that steel. Toss some cheap plastic snap in bushings for metal studs in that hole or something, crap use a piece of heater hose slit down the middle and sleeve that hole where the romex passes through.

Where are you at in PA?
 
I so wish you had done the Go Pro time lapse video thing!!!!
 
Where does the ridge beam connect with the rest of the house?

Are the foundations tied into eachother?
 
use a piece of heater hose slit down the middle and sleeve that hole where the romex passes through.

Where are you at in PA?

Yep, exactly what I did. Split a piece of hose and wrapped it around the romex where it went through the column. But with the wall sealed up, it’s not like the romex is going to rub through the insulation anyway.

Near Harrisburg.

I so wish you had done the Go Pro time lapse video thing!!!!

You’d have seen more activity with the grass growing than with the workshop! :slap:

Where does the ridge beam connect with the rest of the house?

Are the foundations tied into eachother?

Nothing connects to my house. The addition ties into the original workshop. You can see the picture where the column is put in down through the existing roof, through the original workshop wall, and sits on the stem wall. Yes, the wall foundations are tied together. In the following picture you can see where the new block walls tie into the existing walls. The foundations are doweled together and there are ties at each course of block.

img_1448edit-jpg.756336
 
My apologies, I did mean to the workshop. I didn't realize that those images for the post through the knee wall was inside the original workshop.

Keep up the good work!
 
Yep, exactly what I did. Split a piece of hose and wrapped it around the romex where it went through the column. But with the wall sealed up, it’s not like the romex is going to rub through the insulation anyway.

Near Harrisburg.

Sweet! I'm down 81 near Hagerstown. Great looking addition.
 
Back
Top Bottom