I need to vent, I have heard nothing but good things about dakota digital, so earlier this year sent my gauge cluster in to them to have some fancy new gauges put in with a custom logo. Deadline after deadline was missed and got a reply today that they are behind. So i sent them the below. I know you are only seeing one side, mine, so take it with a grain of salt. But ive done my best to remain calm and understanding of the covid 19 situation
**********************
Rick,
Thanks. I have been extremely patient with this project given the covid 19 situation but have been let down time and time again with blown deadlines and missed deliverables. To recap the timeline, so that we are on the same page and you can see the lack of transparency from my perspective.
03/10 - Gauge Cluster arrives at your facility
03/14 - close on VHX, logo, GPS-50-2 - First rendering promised
03/20 - Wanted to set expectation of when i would receive rendering, rendering is a "few weeks out"
04/19 - Checked in again, asking for rendering ( it has been more than "a few weeks out"), No eta given
05/30 - Again requested ETA, inquired about sending gauge cluster back, you reply thanks for patience goal is 7/9, i say thanks and will check back in
7/7 - checking in, told we are delayed, you advise to remit 1/2 payment to get started on the build, i reply i still need to see a rendering but will pay 1/2 in "good faith"
7/29 - no rendering yet but card is run for 929.97
8/10 - email for an update, ask for update on color render and ETA on project, reply "will send you color render"
8/19 - first proactive mail, plan to have the cluster complete in 3-4 weeks (9/19), Do you still require color render? Reply yes still require color render
9/15 - Checking in to make sure we are on track for 9/19 No reply
9/18 - Checking in to make sure we are on track for 9/19, learn that we are backlogged and am offered no ETA.
I want to ask you if this was your project, would you be satisfied with what has been happening? I have asked time and time again for realistic ETAs and would have expected updates if schedules had slipped. I would have been a lot more understanding than waiting for the week of completion.
What is your proposal to handle the above?
-Andrew
*************************
Maybe im foolish to give them one last chance, i should probably end our relationship and get the gauge cluster back. I am extremely disappointed in lack of professionalism here....
**********************
Rick,
Thanks. I have been extremely patient with this project given the covid 19 situation but have been let down time and time again with blown deadlines and missed deliverables. To recap the timeline, so that we are on the same page and you can see the lack of transparency from my perspective.
03/10 - Gauge Cluster arrives at your facility
03/14 - close on VHX, logo, GPS-50-2 - First rendering promised
03/20 - Wanted to set expectation of when i would receive rendering, rendering is a "few weeks out"
04/19 - Checked in again, asking for rendering ( it has been more than "a few weeks out"), No eta given
05/30 - Again requested ETA, inquired about sending gauge cluster back, you reply thanks for patience goal is 7/9, i say thanks and will check back in
7/7 - checking in, told we are delayed, you advise to remit 1/2 payment to get started on the build, i reply i still need to see a rendering but will pay 1/2 in "good faith"
7/29 - no rendering yet but card is run for 929.97
8/10 - email for an update, ask for update on color render and ETA on project, reply "will send you color render"
8/19 - first proactive mail, plan to have the cluster complete in 3-4 weeks (9/19), Do you still require color render? Reply yes still require color render
9/15 - Checking in to make sure we are on track for 9/19 No reply
9/18 - Checking in to make sure we are on track for 9/19, learn that we are backlogged and am offered no ETA.
I want to ask you if this was your project, would you be satisfied with what has been happening? I have asked time and time again for realistic ETAs and would have expected updates if schedules had slipped. I would have been a lot more understanding than waiting for the week of completion.
What is your proposal to handle the above?
-Andrew
*************************
Maybe im foolish to give them one last chance, i should probably end our relationship and get the gauge cluster back. I am extremely disappointed in lack of professionalism here....