Well it was snowing and blowing yesterday I finally got the metal that was laying in my garage put up. Now I need to find a trolley/lift. Prolly H.F. but will be shopping around.
1. Drilled 3/8 holes in 3/8 base plate.
2. Mounted base plates with 3/8 expansion threaded expansion studs. They went 3.5 inch deep. None went through the slab because plates are mounted over footing locations.
3. Cut 3 inch .188 wall posts to seven feet.
4. Welded I-beam plates (1/4 inch 6"x6") pre-drilled to match top plate.
5. Welded top post plates.
6. Tacked and held 1 post with straps.
7. Hoisted and ratchet strap beam on to 1 post and dropped two long bolts through to allow movement of second post.
8. Bolted second post to low and and dragged it up with top beam.
9. used 8 grade 10.9 M10 Cap Bolts.
10. Plumbed posts and finshed weld base plates.
it was a long day, but can't wait to hang a 2F from there.
1. Drilled 3/8 holes in 3/8 base plate.
2. Mounted base plates with 3/8 expansion threaded expansion studs. They went 3.5 inch deep. None went through the slab because plates are mounted over footing locations.
3. Cut 3 inch .188 wall posts to seven feet.
4. Welded I-beam plates (1/4 inch 6"x6") pre-drilled to match top plate.
5. Welded top post plates.
6. Tacked and held 1 post with straps.
7. Hoisted and ratchet strap beam on to 1 post and dropped two long bolts through to allow movement of second post.
8. Bolted second post to low and and dragged it up with top beam.
9. used 8 grade 10.9 M10 Cap Bolts.
10. Plumbed posts and finshed weld base plates.
it was a long day, but can't wait to hang a 2F from there.