Hello,
This spring I poured a concrete slab for a work area: 16' wide, 22' deep and a 6" thick pour with 3/8" rebar on 10" grid. Let it cure up and went on a steel quest for uprights and horizontal frame. Found some 6" x 9" x 3/8ths thick I-beams that were 9'11" long and some 5" x 10" x 30' long and 1/2" thick I beams for the horizontal box. Welded some caps on the uprights for bolting to the slab and welding to the horizontal sections. The horizontal box was mitered with a oxyacetelyne torch and stick welded with 6011 rod. The beam for the trolley is the next quest. In the mean time here are a few flicks:
Hola
eric
This spring I poured a concrete slab for a work area: 16' wide, 22' deep and a 6" thick pour with 3/8" rebar on 10" grid. Let it cure up and went on a steel quest for uprights and horizontal frame. Found some 6" x 9" x 3/8ths thick I-beams that were 9'11" long and some 5" x 10" x 30' long and 1/2" thick I beams for the horizontal box. Welded some caps on the uprights for bolting to the slab and welding to the horizontal sections. The horizontal box was mitered with a oxyacetelyne torch and stick welded with 6011 rod. The beam for the trolley is the next quest. In the mean time here are a few flicks:



Hola
eric