Amp wired up, fused, sub mounted and wired, and the ve.direct cable installed which fixed the mppt monitoring problem. The sub bumps! Thanks @Hokie LX for the sub, you're the mvp!
Ready for GSMTR next week!
Sunny day example of power generation, at about 10am. A little over 400w. Don't need to keep the motel plugged in anymore! Note the negative DC power rating in the bottom square.
Have a plan to fix solar generation monitoring, will have it in...
Solar install complete. Monitoring is a little odd, seems I can't connect both my Epoch battery and the SmartSolar MPPT to my Color Control GX via VE.can, since the battery needs a different baud rate than the MPPT. Even though there are two...
I'm not sure how much heat it'll put off to be honest, or if it turns off, solid questions! I know it has charging profiles set up within it, meaning it stops charging the battery when it hits a certain voltage, but I'm not sure it ever turns...
Got to the interior wiring this afternoon. Built a panel to mount components to, and skinned it with aluminum, since the component spec is to mount to a non-flammable surface.
Once that was done, I got to work. Pretty happy with how it neat it...
Got the last panel up this morning, things sealed up, all panels wired in series, and connected to the entry gland. 127ish volts measured from the leads inside, means success. Next up, inside work, getting the controller mounted and wired.
Neglected to order mounting feet for the last panel, but got a good amount done today. Removed both roof vents and filled the holes with some aluminum siding sheet left over, then mounted three panels and the cable entry gland. Good day.
Last...