- Thread starter
- #41
We were a bit worn out after two days of assembly so we set a modest goal yesterday of getting the last post and the middle 15' tie beam placed. There was no way to get the tractor in to lift the tie beam directly into position so I had to get a little creative again with the forks and some 4x4s. It actually went together easier than I thought although those fully housed tie beam joints are very tight. Using ratchet straps and a little sledgehammer persuasion and they eventually hit home. That went well enough that we decided to go ahead and put the second 24' beam into place. Given that the cook shed site is built up a couple of feet in the front my tractor fork tips could just barely get that beam over the post tenons; we literally only had a couple of inches to spare. Thankfully though it did work. What a great feeling when that last beam went into place. Three days to erect what took over three weeks to prep. Not too bad considering that there was just two of us the last two days.
I still have to finish driving in all the pegs but it's nice to have all the posts and beams up to the 10' level. The plan now is to get the slab poured. Need to get the imbedded sections of electrical conduit installed and hopefully get the concrete poured in the next few days. I still have to finish the ridge beam and its associated king posts (3) and knee braces (4). Not keeping score per se but that's only 11 mortise and tenon joints left out of a total of 54 for the building!
I'm also changing directions on the rafters. I bought rough sawn 2x8s to the same marine treatment spec but after erecting the massive 8x8 posts and beams I am concerned that they are going to look a little light. Not that they aren't plenty large enough for the span but maybe not in keeping with the scale of everything else. Currently getting pricing and availability of larger lumber from my Gulf Coast supplier.
I still have to finish driving in all the pegs but it's nice to have all the posts and beams up to the 10' level. The plan now is to get the slab poured. Need to get the imbedded sections of electrical conduit installed and hopefully get the concrete poured in the next few days. I still have to finish the ridge beam and its associated king posts (3) and knee braces (4). Not keeping score per se but that's only 11 mortise and tenon joints left out of a total of 54 for the building!
I'm also changing directions on the rafters. I bought rough sawn 2x8s to the same marine treatment spec but after erecting the massive 8x8 posts and beams I am concerned that they are going to look a little light. Not that they aren't plenty large enough for the span but maybe not in keeping with the scale of everything else. Currently getting pricing and availability of larger lumber from my Gulf Coast supplier.
, we all agreed on 6" of 4000 psi fiber mesh reinforced concrete with a 6" turndown around the perimeter (12" total thickness on the edges for ~ 1'). The posts make using wire mesh problematic and the fiber mesh shouldn't be an issue with the finish as we are going hard hand troweled on this slab. There is no need for rebar around the perimeter as the posts are taking all the load. They will frame for the slab with a 1% slope towards the front (2" total drop back to front). The top of the step down will get a very light broom finish. There was a lot of discussion about cut joints. I generally try to minimize them but I have never poured a slab with wood posts imbedded. Concrete guy has done many post frame buildings and convinced us to use a very interesting cut pattern radiating from the posts. Hard to describe so I will just post photos when it's done.